BUILDING PROJECT BLOG
FIREPLACE ALL FINISHED(MARCH 17, 2023)
FIREPLACE GAS LINE(JANUARY 19, 2023)
FIREPLACE RENOVATION SCREEN BY DEL MARTIN(NOVEMBER 2022)
ONE MORE FINISHING TOUCH(JUNE 24, 2022)
ARCHITECT’S PHOTO SHOOT(OCTOBER 28, 2021)
NEW SIGN(OCTOBER 26, 2021)
LANDSCAPING (JULY 19, 2021)
LIGHTING PROJECT COMPLETION(JUNE 18, 2021)
DONOR RECOGNITION(MAY 20, 2021)
CLEANING AND RESTORING THE WWI MONUMENT PLAQUE(AUGUST 19, 2019)
THANKS TO ALL THE INSPECTORS — ESPECIALLY THE BUILDING COMMISSIONER (JUNE 29, 2019)
WAITING FOR THE FINAL INSPECTIONS! (JUNE 24, 2019)
ONE OF THE FINAL TOUCHES (JUNE 21, 2019)
THE FRONT DOOR ARRIVES (JUNE 18, 2019)
ALMOST THERE (JUNE 15, 2019)
GUESS THE LETTERING, FINISHING TRIM ON THE MULTIPURPOSE ROOM (JUNE 13, 2019)
FINISHING TOUCHES EXTERIOR AND INTERIOR (JUNE 12, 2019)
STARTING UP THE HEAT AND AC, FINISHING SIDING AND EXTERIOR NEAR GRADE (JUNE 11, 2019)
EXTERIOR LIGHTING, GRASS SEEDING AND MOBILE BOOK CASES (JUNE 10, 2019)
CRABAPPLE TREE PLANTED, PATH LIGHT BOLLARD INSTALLED, AND CARPET IN THE MULTIPURPOSE ROOM (JUNE 7, 2019)
PARKING LOT STRIPING, CIRCULATION DESK SURFACE, AND CARPET (JUNE 6, 2019)
PARKING LOT! (JUNE 4, 2019)
FINAL PLUMBING INSPECTION PASSED! SOLAR POWERED TOILETS WORKING. PREPARATION FOR TOMORROW’S PAVING, DECK COMPLETED, LAST CONRETE PATH POURED, AND MOBILE SHELVING DELIVERED (JUNE 3, 2019)
FENCE REMOVED, LANDSCAPING BEGINS, WORK STATION ARRIVES (MAY 31, 2019)
MULTIPURPOSE ROOM LIGHTING (MAY 30, 2019)
PLAZA AND WALKWAY POURED, ROOF WORK, WATER FOUNTAIN INSTALLED (MAY 29, 2019)
DECK RAILING WORK (MAY 28, 2019)
MEMORIAL DAY 2019
ELIMINATING THE STEP THE ORIGINAL FRONT STEP FROM 1931, KITCHEN AND BATHROOM WORK (MAY 24, 2019)
SEPTIC TANK INSTALLED, GUTTER WORK, AND BASEMENT RAMP RAILING (MAY 23, 2019)
FLAGPOLE! FINISH GRADES IN BACK (MAY 22, 2019)
PREP FOR GUTTERS, WIFI AND INTERNET CONNECTIONS, MORE SHELF WORK (MAY 21, 2019)
BACK RAMP POURED, COLUMN INSTALLED, AND LIGHTING LIT(MAY 20, 2019)
FINISH CARPENTRY INSTALL CONTINUES WITH DIRECTOR’S DESK, STAFF CLOSET AND CHILDREN’S AREA STORAGE (MAY 17, 2019)
CIRCULATION DESK INSTALL, SEPTIC CONTINUED, PREPARATION FOR THE REST OF THE BACK RAMP (MAY 16, 2019)
PROPANE TANK INSTALLED, SEPTIC PREPARATION, UPPER RAMP TO BACK POURED (MAY 15, 2019)
FRONT STOOPS POURED, FOUNDATION DRAIN DAYLIGHTED (MAY 13, 2019)
MORE FINISH CARPENTRY AND FIRST LIGHT FIXTURE IN NEW MAIN ROOM (MAY 10, 2019)
DROP CEILINGS IN STAIRWELL, KITCHENETTE, QUIET ROOMS, AND DECK FLOOR COMPLETED(RAILING IS TEMPORARY) (MAY 9, 2019)
ACOUSTICAL TREATMENT FOR THE MULTIPURPOSE ROOM (MAY 8, 2019)
EXTERIOR PAINT AND DECK STARTED (MAY 7, 2019)
SHELVES! (MAY 6, 2019)
WAITING FOR THE SHELVING (MAY 3, 2019)
WORK ON DECK, PAINTING AND WINDOW TRIM (MAY 2, 2019)
BATHROOM PAINTED, MORE FINISH CARPENTRY, DECKING ARRIVES (MAY 1, 2019)
DRIVEWAY WORK, BASE OF BOOKS SHELVES AND WALK OFF MAT IN ENTRY (APRIL 30, 2019)
DRIVEWAY SIDEWALK PREP, CEILING BEAM PROGRESS (APRIL 29, 2019)
BASEMENT LIGHTS WORKING, TILE PROGRESS, SUBFLOOR IN MULTIPURPOSE ROOM AND GUARD RAIL START (APRIL 26, 2019)
PERMANENT ELECTRIC HOOK UP, MORE TILE, DRIVEWAY GOING IN, AND GETTING READY TO SAY GOODBYE TO THE TRAILER (APRIL 25, 2019)